Run-9 Schedule Milestones
Paul Sampson's maintenance/startup schedule is a available
here.
His injector startup schedule as of Jan. 5 is available
here.
Mei Bai's Startup plan is available here
Milestones | Progress | |
11/21/2008 | NSRL Run 08C ends | NSRL 08C is finished. The run was extended to 11/22/08. |
12/02(05)/2008 | Beam in and possibly after the first Linac Tank | Delayed, 01/05/09 29 mA BLIP beam after tank 2 |
~12/10/2008 | Beam at the end of the Linac | Delayed, see the Journal note on 01/09/09 |
~12/23/2008 | Linac ready to deliver beam to BLIP | Delayed (delivered on 01/12/2009) |
01/05/2009 | BLIP operations begin | Delayed, see the Journal note on 01/09/09 |
01/10/2009 | RHIC cooldown to 45 K | RHIC cooldown on time. Yellow cooldown delayed by broken valve boxes. Fixed. No delay on 4.5 K cooldown is expected. |
01/12/2009 | Beam in Booster | On time, beam to BLIP on 01/12/2009 |
01/19/2009 | Beam in AGS | Beam to AGS on Time |
02/02/2009 | Blue Ring 45K to 4.5K cooldown begins, Cooldown will take ~3-3.5 Days. Blue ring is ready for injection 2 days later. | Blue cooldown to 4.5 K has begun on 02/02/2009, progresses well. |
02/05/2009 | Yellow Ring 45K to 4.5K cooldown begins, Cooldown will take ~3-3.5 Days. Yellow ring is ready for injection 2 days later. | Yellow cooldown to 4.5 has begun on 02/03/2009. |
02/07(08)/2009 - 02/14/2009 |
Injection in Blue and Yellow rings
|
|
02/15/2009 - 02/16/2009 |
LLRF ramp and 9MHz cavity commissioning.
|
|
02/17/2009 - 02/27/2009 |
Ramp development and store optimization
|
|
02/28/2009 | Delivered colissions | |
03/01/2009 - 03/02/2009 |
Rotator Ramp development | |
~03/08/2009 | NSRL Run 09 begins |