4/18/00
(Continue Yellow Ring PS testing ……)
April 18 - 20 Warm up the Yellow Ring sector 5
April 20 (eve) Bleed up
Blue Sector 5 vacuum + triplet
April 21 Open blue ring Q3 cryostat - 12 hrs
Splice in new voltage tap leads - 12 hrs
Pump down/leak check - 24 hrs
Cool down blue and yellow ring sextant - 48
hrs
http://www.cadops/AGS/Operations/RElist/ringentry.html