Makdisi

4/18/00

Schedule

 

April 14-16  Warm up the Blue Ring Sector 5

 

April 16                 Repair the shorts

 

“New and Improved Plan”

 

April 17                 Finished Yellow Ring PS testing in sector 5

                              (Continue Yellow Ring PS testing ……)

 

April 18 - 20          Warm up the Yellow Ring sector 5

 

April 20 (eve)        Bleed up Blue Sector 5 vacuum + triplet

 

April 21                  Open blue ring Q3 cryostat - 12 hrs

                              Splice in new voltage tap leads - 12 hrs

                              Close cryostat - 12 hrs

                              Pump down/leak check - 24 hrs

                              Cool down blue and yellow ring sextant - 48 hrs

 

April 26                  Ready to resume RHIC Commissioning

 

During this phase the IRs will be on Restricted Access
 
Request for Access should be through the C-A Provided 
x-terminals which are on a special subnet.

http://www.cadops/AGS/Operations/RElist/ringentry.html

 